When estimating for labor, budgeting a person’s wage will get you close enough?
The following are needed when computing your owned equipment?
Performance and payment bonds are only provided by the prime contractor for the project owner?
Overhead costs are typically those expenses that can not easily be connected to a specific project?
Margin is equal to Markup?